Roads & Highways Completed 2018

Construction of Approach Road Up to Phase-3 Field A & B – MBR Solar Park

Mohammed Bin Rashid Al Maktoum Solar Park Dubai, UAE 2018
Overview

Approach roads serving Phase 3 Field A and B at the MBR Al Maktoum Solar Park, establishing reliable access for construction teams, heavy equipment and logistics operations.

Tanveer Ahmed Road Contracting LLC (TARC) successfully completed the construction of approach roads serving Phase 3 Field A and Field B of the Mohammed Bin Rashid Al Maktoum Solar Park. The project was designed to establish reliable site access for construction teams, heavy equipment, and logistics operations supporting one of the UAE’s landmark renewable energy developments.

The works required precise earthworks, road formation, grading, and pavement construction while maintaining strict quality control and environmental compliance. Through careful planning and efficient execution, TARC delivered durable infrastructure that supported the timely progression of subsequent construction activities.

Scope of work

  • Approach road construction
  • Site grading and earthworks
  • Subgrade preparation
  • Road base installation and compaction
  • Asphalt paving works
  • Drainage coordination
  • Road signage and safety installations
  • Material testing and quality assurance
8 km
Approach Roads Constructed
2018
Successfully Delivered
100%
Quality Standards Met
Zero
Lost-Time Incidents
How it ran

Project timeline

Phase 01

Survey, Design Review & Mobilisation

Engineering surveys, route verification, project planning, and site mobilisation were completed before construction commenced.

Phase 02

Earthworks & Formation

Bulk excavation, grading, and preparation of the road formation were carried out to achieve the required engineering specifications.

Phase 03

Road Construction & Asphalt Works

Road base installation, compaction, asphalt paving, drainage coordination, and safety features were completed under continuous quality monitoring.

Phase 04

Inspection, Testing & Completion

Final inspections, material testing, client verification, and project handover were completed in accordance with approved project requirements.