Overview

Access road to the Innovation Center at the MBR Al Maktoum Solar Park — safe, durable connectivity for visitors, operational staff and ongoing development.

Tanveer Ahmed Road Contracting LLC (TARC) completed the construction of the access road serving the Innovation Center at the Mohammed Bin Rashid Al Maktoum Solar Park. The project was designed to provide safe, durable, and efficient access to one of the UAE’s flagship renewable energy and sustainability facilities.

The works involved comprehensive road construction activities, including earthworks, pavement layers, drainage integration, and traffic management. Delivered with strict adherence to engineering specifications and HSE requirements, the project supports seamless connectivity for visitors, operational staff, and ongoing development within the Solar Park.

Scope of work

  • Access road construction
  • Site clearance and earthworks
  • Subgrade preparation
  • Road base and asphalt paving
  • Surface water drainage works
  • Kerb and edge detailing
  • Road signage and markings
  • Quality testing and project commissioning
5 km
Access Road Constructed
2019
Project Completed
100%
Specification Compliance
Zero
Major Safety Incidents
How it ran

Project timeline

Phase 01

Project Planning & Site Preparation

Engineering surveys, route planning, approvals, and mobilisation activities were completed before construction commenced.

Phase 02

Earthworks & Road Foundation

Excavation, grading, subgrade preparation, and road base installation established a stable foundation for the access road.

Phase 03

Road Construction & Finishing Works

Asphalt paving, drainage works, kerb installation, road markings, and safety features were completed under continuous quality supervision.

Phase 04

Inspection & Client Handover

Final quality inspections, material testing, compliance verification, and client approvals were completed before project handover.